City Council approved $644,782 more for PSL BMX at Tradition Regional Park on Nov. 9, for a food truck courtyard and a restroom and concession building.
PSL BMX, the city’s adaptive BMX park at Tradition Regional Park, is getting a food truck courtyard and a building with restrooms, a concession stand and offices. The Port St. Lucie City Council approved adding $644,782 to the construction contract to pay for both.
Updated Nov. 11: The council approved the amendment Nov. 9 as part of its consent agenda, passed unanimously by voice vote with no discussion of this item, the city’s legislative record shows. The city’s PSL BMX page still gives the opening as late 2026 or early 2027. Our council story covers the rest of the meeting.
With the amendment, the contract with Action Sports Design LLC of Austin, Texas, rises to $6,881,344. The city awarded it at $5,889,252.39 in June 2025, according to the original contract.
What the money buys
The signed Amendment 8 covers two change orders.
The restroom, concession and administration building: $565,735.
- $95,163 for design: $65,600 to ADC Architects and $29,563 for the Action Sports Design team
- $470,572 for construction
The building contract with Treasure Coast General Contractors LLC is $827,265. The city is not paying all of that again. The existing contract already held a $325,000 line for a building, and the $31,693 concrete slab is already under contract, so both come off.
The building has seven exterior doors, impact-rated windows and a roll-up service door. The change order lists concession, training and restroom rooms. It leaves out fire sprinklers, landscaping, cabinets, countertops, paving and underground utilities.
The food truck courtyard: $79,047.
- about 5,919 square feet of concrete for a walkway, a drive and picnic-table pads
- synthetic turf
- design, contractor fees and the bond cost
The contractor puts the courtyard work at 14 days, built alongside the rest of the job.
How the contract has grown
The city’s file of Amendments 1 to 7 shows two earlier changes to the price:
- Amendment 3 cut the total by $237,690.39, to $5,651,562. The city bought pipe, tubing, fittings and rebar directly, which saves sales tax.
- Amendment 4 added $585,000 for a parking lot, bringing the total to $6,236,562. The council also set aside a 5% city-held contingency, $29,250, for that work.
The other amendments extended the contract’s end date. It now runs to Jan. 31, 2027.
Rounded, the totals are $5.89 million at the award, $5.65 million after Amendment 3, $6.24 million after Amendment 4 and $6.88 million after Amendment 8. That is about $992,000, or 17%, more than the 2025 award.
What PSL BMX is
The city’s PSL BMX page says the park is “under construction and anticipated to open in late 2026 or early 2027.” The city calls it the first fully inclusive BMX facility of its kind in the United States. It is built for bicycles and for adaptive cycles, skateboards, skates, scooters and remote-control cars.
The city lists:
- a 1,100-foot USA BMX-sanctioned track with an adaptive surface
- a timed competition pump track and a jump line
- a quarter-mile drag strip for 1/10-scale remote-control cars
- a children’s bicycle safety and learning area
Programs are to include USA BMX racing, clinics by age, after-school programs, summer camps and free open riding on Sundays.
Tradition Regional Park covers 110 acres about a quarter-mile from the end of SW Tradition Parkway at the Fern Lake roundabout. PSL BMX is its first phase.
What it means for you
- Families in Tradition and western Port St. Lucie will have food trucks, a concession stand and restrooms on site when the park opens.
- No opening date yet. The city still says late 2026 or early 2027. Race schedules and memberships will be posted on the USA BMX track page.
- Questions about the spending can go to your council member. Our who to call at City Hall page has the numbers.
More on the city’s parks, including Torino Regional Park and Stars and Stripes Park, is on our parks and trails guide.
Have your say